Update – Refurbishment Bld 141

23rd November 2015
The refurbishment of building 78, 131, 139, 141 and 142 is now well underway, with the soft strip of all services now completed through 50% of the project.  Today has seen the first fix of traywork and services beginning in earnest in building 141.  The contractor is confident that the the works will be complete for the grand opening in April 2016.
Bld 141 Soft Strip